施工用电施工组织

2022-07-11 来源:飒榕旅游知识分享网
目 录

第1章 编制依据 ···························································································· 1 第2章 工程概况 ···························································································· 1 第3章 现场临时用电设置 ············································································· 1

3.1电源提供点 ·································································································································· 2 3.2现场供电系统 ······························································································································ 3 3.3施工现场1000KVA变压器的用电设备统计明细表 ···································································· 4

第4章 变压器容量核算 ················································································· 4

4.1计算现场用电容量 ······················································································································ 5 4.2变压器供电范围确定 ·················································································································· 6 4.3根据高峰期主要施工用电设备及相应功率计算,变压器施工用电 ·········································· 6

第5章 电缆截面选择及电压降核算 ····························································· 7

5.1导线截面计算 ······························································································································ 7

第6章 现场线路布置 ·················································································· 10

6.1电缆电线设置 ···························································································································· 10

第7章 保护接零、接地与防雷要求 ····························································· 11

7.1接零保护的定义 ························································································································ 12 7.2接零保护的优点 ························································································································ 12 7.3接零保护的实施:保护零线的要求和设置 ·············································································· 13

第8章 临时用电施工技术要求 ······································································ 14

8.1变压器及配电线路的布置 ········································································································· 15 8.2临时供电 ··································································································································· 16 8.3场地用电的安装工艺与要求 ····································································································· 16

i

8.4施工照明 ··································································································································· 17 8.5施工用电线路 ···························································································································· 18 8.6配电箱的设置 ···························································································································· 19 8.7电缆的安装架设 ························································································································ 21 8.8施工现场变配电维修以及注意事项 ·························································································· 22

第9章 安全用电措施 ·················································································· 23

9.1电工职责 ··································································································································· 24 9.2安全用电技术措施 ···················································································································· 25

第10章 电气线路的火灾原因及预防措施 ···················································· 32 第11章 触电事故的应急预案 ······································································ 35

11.1防触电事故的措施: ·············································································································· 35 11.2触电事故的应急预案 ·············································································································· 36

第12章 冬雨季安全用电措施 ···································································· 37

12.1电气安装工程 ·························································································································· 37 12.2施工机械设备安全使用 ··········································································································· 38

第13章 附图 ······························································································· 40

ii

第1章 编制依据

《施工现场临时用电安全技术规范》(JGJ46-2005)。 《建筑施工安全检查标准》(JGJ59-99)、

《建设工程施工现场供电用电安全规范》(GB50194-93)、 《建筑工程施工现场供电安全规范》GB50194-93中国建筑工业出版社

《通用用电设备配电设计规范》GB50055-93中国建筑工业出版社

《供配电系统设计规范》GB50052-95中国建筑工业出版社 《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社

根据本项目工程特点、重点及难点,按业主提供的施工场地及工期要求,结合周边环境的特点合理安排施工场地布置。施工场地的临时用电设备布置应符合轨道交通公司及指挥部对建设工程的管理规定。

第2章 工程概况

贵阳市窦官~贵阳火车北站一号线交通市政配套工程土建施工7标,包括下麦西站(不含站前广场)、下麦西站~将军山站区间、将军山站、将军山~云潭路站区间高架部分。起讫里程YC1K0+697.750 ~YC1K2+852.52,线路长度2.1547km。

其中主要工程车站2座(下麦西站YC1K0+697.750~YC1K0+818.200,将军山站YC1K2+391.5~YC1K2+511.5),下麦西隧道1座(YC1K1+330 ~YC1K1+805,

1

长475m),区间高架桥3段(下麦西站~将军山站区间高架两段: 下麦西1号大桥C1K0+945.98 ~YC1K1+306.48长360.5m,下麦西2号特大桥YC1K1+873.27 ~YC1K2+391.5长518.23m,将军山站~天潭路站区间高架:将军山大桥YC1K2+511.850~YC1K2+852.52长340.67m。下麦西站~将军山站区间框架桥(YC1K0+910 1-8.0m)。下麦西站~将军山站区间路基(YC1K0+818.25~YC1K0+945.98长127.73m、YC1K1+306.48~YC1K1+330长23.52m、YC1K1+850~YC1K1+873.26长23.26m)。

第3章 现场临时用电设置

3.1电源提供点

施工现场引入两台1000KVA箱式变压器,一台安装在将军山大桥旁(为S1),另一台安装在下麦西隧道洞口处(为S2),项目部用电从S1变压引入,S1变压供将军山大桥,将军山车站、下麦2号大桥用电,后期也供下麦西隧道用电。S2供下麦西隧道、下麦西1号大桥、下麦西站用电。

项目部用电从S1引入一条YJLV3*120+2*70m²电缆115米,装设有一个7回路配电箱。室内主线用绝缘线管穿设,每栋每层各设有总漏电开关,各层单独从二级箱引线,食堂、卫生间有单独漏电开关。办公区一层、二层和住宿一层、二层采用动力和照明分开敷设的方式。食堂、会议室、卫生间混合方式敷设。

项目部临时用电平面图、系统图见附图一、附图二, 施工现场临时用电平面布置图见附图三, S1、S2变压器临时用电系统图见附图四、五。

2

3.2现场供电系统

施工现场及项目部用电采用TN—S接零保护系统,三相五线制供电。

供配电方式:由施工现场提供箱式变压器处配电接口引出电源至施工现场总配电柜(一级配电箱),再由总配电柜分配给各分配电二级电箱,最后由二级电箱接至开关箱控制用电设备。供电方式采用三相五线制TN-S系统。在总配电箱及中间、末端箱处,以及超过100m的箱内做重复接地。工作零线和保护零线要严格区分,不得混用。所有机电设备的金属外壳必须与保护零线做可靠的电气联接。根据现场情况总配电柜(箱)出线采用放射式和树干式相结合的配电方式。对负荷比较大的空压机、风机采用单独回路配电,对负荷较远且较小的木工机械、钢筋机械电源可采用树干式配电方式。

施工现场配电线路:施工现场主要干线采用橡套电缆、隧道进出口、各个车站、各个大桥、搅拌站、项目部照明、加工机械及埋地处电源线采用橡套电缆穿管敷设或者挖沟加盖板埋地敷设,移动式配电箱和开关箱的进、出线必须用橡皮绝缘电缆。

3

3.3施工现场S1(1000KVA)变压器的用电设备统计明细表

序单 数 设备功率总功率设 备 名 称 设 备 型 号 号 位 量 (KW) (KW) 搅拌机 JS750 台 1 60 60 1 电焊机 BXl-500 台 10 21 210 2 电动空压机 V—3 台 16 18.5 296 3 钢筋弯曲机 2X—20 台 6 3 18 4 钢筋调直机 GT6—12 台 3 3 9 5 MQ3225 台 1 0.4 0.4 6 轻型台式砂轮机 钢筋切断机 E3—36 台 3 2.2 6.6 7 JC38 台 10 1.5 15 8 混凝土振捣棒 水泵 BXl-315 台 5 7.5 37.5 9 项目部照明 套 1 10 10 10 套 1 30 30 11 三相动力(食堂) 现场照明 套 1 20 20 12 现场生活区 套 1 30 30 13 项目部动力 套 1 68 68 14 变压器S1施工用电设备总功率:810.5KW 备 注 3.4施工现场S2(1000KVA)变压器的用电设备统计明细表

序设 备 名 称 号 搅拌机 1 二衬台车 2 电焊机 3 喷锚机 4 电动空压机 5 钢筋弯曲机 6 钢筋调直机 7 8 轻型台式砂轮机 钢筋切断机 9 注浆机 10 11 混凝土振捣棒 水泵 12 送风机 13 现场照明 14 办公 15 生活区 16 设 备 型 号 JS750 BX1-500 V—110 2X—20 GT6—12 MQ3225 E3—36 DQG-30 JC38 BXl-315 单 数 位 量 台 台 台 台 台 台 台 台 台 台 台 台 台 套 套 套 1 1 5 2 2 2 2 1 1 2 10 5 1 1 1 1 设备功率(KW) 60 60 21 11 146 3 3 0.4 3 3 1.5 7.5 110 20 35 30 总功率(KW) 60 60 105 22 292 6 6 0.4 3 6 15 37.5 110 20 35 30 备 注 变压器S2施工用电设备总功率:807.9KW 4

第4章 变压器容量核算

4.1计算现场用电容量

取最高用电需求阶段

公式:Sj=1.05~1.10*[(K1P1/cosφ)+K2P2+K3P3+K4P4]

Sj——总视在计算负荷或总容量(KVA) P1——电动机额定功率(KW) P2——电焊机额定功率(KW) P3——室内照明容量(KW) P4——室外照明容量(KW)

cosφ——电动机的平均功率因数(0.75~0.78) K1、K2、K3、K4——需用系数,见下表:

用电设备 数 量 (台) 3-10 一般电动机 11-30 30以上 动力设备 电焊机 3-10 10以上 5

需 要 系 数 0.7 K1 0.6 0.5 0.5 K2 0.6 0.5

室内照明 室外照明 K3 K4 0.8 1.0 4.2变压器供电范围确定

根据现场流水段划分,工作内容包括:搅拌机作业、电焊机作业,送风机作业,空压机作业、钢筋调直机作业等。用电高峰期同时作业包括:搅拌机作业、电焊机作业,送风机作业,空压机作业、钢筋调直机作业、现场照明等。同时根据工期和现场提供电源功率综合考虑,施工计算如下:

4.3根据高峰期主要施工用电设备及相应功率计算,S1变压器施工用电

P1:电动机总功率(KW)计算得 P1=630.5KW P2:电焊机总功率(KW)计算得 P2=210KW P3:室内照明总功率(KW)计算得 P3=10KW P4:室外照明总功率(KW)计算得 P4=20KW 计算得出变压器有效功率为:

Sj=1.05*[0.6*630.5/0.75+0.6*210+0.8*10+1*20]=691.32

(kVA)

变压器的选择:根据变压器S1 =1000kVA引出电源至施工现场容量Sj =691.32KVA与设计总容量Sj比较,S1> Sj,则引至施工现场的电源可满足施工用电需要。

6

4.4根据高峰期主要施工用电设备及相应功率计算,S2变压器施工用电

P1:电动机总功率(KW)计算得 P1=627.9KW P2:电焊机总功率(KW)计算得 P2=105KW P3:室内照明总功率(KW)计算得 P3=55KW P4:室外照明总功率(KW)计算得 P4=20KW 计算得出变压器有效功率为:

Sj=1.05*[0.6*627.9/0.75+0.6*105+0.8*55+1*20]=660.78

(kVA)

变压器的选择:根据变压器S2 =1000kVA引出电源至施工现场容量Sj =660.78KVA与设计总容量Sj比较,S2> Sj,则引至施工现场的电源可满足施工用电需要。

第5章 电缆截面选择及电压降核算

5.1导线截面计算

I=k k1 P/

3Ucos(公式)

I----回路电流(A) k----安全系数(取1.05)

k1----需用系数(动力系数0.5~0.7,焊机系数0.5~0.6,

照明系数0.8~1.0)

7

P-----回路总功率(W)

cos-----功率因数临时取0.70~0.75 U----三相电压380V

5.1.1变压器控制线路

1)、变压器S1线路选择布设:

根据现场临时用电布置以及现场用电设备的布置须从箱变引出4根电缆至现场4台A1一级配电柜(箱),为: 3*185+2*95mm2三根,3*120+2*70 mm2一根,然后由一级配电柜(箱)分接至现场各个桥所需的分配电箱。

2)、箱式变压器S1至现场一级配(箱)电柜电缆的选择: (1)A1-01一级配电箱:P=163KW(空压机8台,水泵2台) 计算得电流为: I=k k1 P/

3Ucos =1.05*0.7*163*1000/3*380*0.75=242.7A

为确保使用过程中临时分路用电,故选择YJLV 3*185+2*95mm2

可以满足施工需要。

(2)A1-02 一级配电箱 搅拌机生活区用 P=120KW 计算得电流为: I=k k1 P/

3Ucos =1.05*0.7*120*1000/3*380*0.75=178.6A

故选择YJLV 3*185+2*95mm2可以满足施工需要。 (3)A1-03 一级配电箱 项目部 P=108KW 计算得电流为: I=k k1 P/

3Ucos =1.05*0.8*108*1000/3*380*0.75=183.7A

8

此回路确保临时分线路用电,故选择YJLV 3*120+2*70mm2可以满足施工需要。

(4)A1-04 一级配电箱 钢筋场地 P=120KW 计算得电流为: I=k k1 P/

3Ucos =1.05*0.8*120*1000/3*380*0.75=204A

故选择YJLV 3*185+2*95mm2可以满足焊机使用。 注:大型设备直接从一级电箱接入设备的专用箱。 3)、由S2引至施工现场一级配电柜(箱)电缆的选择: (1)A1-01一级配电箱洞口空压机及洞内用电:P=196KW 计

I=k

k1

P/

3Ucos

=1.05*0.7*196*1000/3*380*0.75=291A

为确保使用过程中临时分路用电,故选择YJLV 3*240+2*120mm2

可以满足施工现场用电需要。

(2)A1-02一级配电箱生活区及搅拌机用:P=135KW 计

I=k

k1

P/

3Ucos

=1.05*0.7*135*1000/3*380*0.75=201A

为确保使用过程中临时分路用电,故选择YJLV 3*240+2*120mm2

可以满足现场用电需要。

(3)A1-03二级配电箱洞口用:P=209KW 计

I=k

k1

P/

3Ucos

=1.05*0.7*209*1000/3*380*0.75=311A

为确保使用过程中临时分路用电,故选择YJLV3*240+2*120mm2

9

可以满足洞口用电需要。

(4)A1-04一级配电箱下麦西1号大桥、下麦西站用:P=154KW 计

I=k

k1

P/

3Ucos

=1.05*0.8*154*1000/3*380*0.75=262A

为确保使用过程中临时分路用电,故选择YJLV 3*240+2*120mm2可以满足施工现场用电需要。

第6章 现场线路布置

现场电箱的布置见临电平面布置图。由现场施工临时变压器引出至一级配电柜,再由一级配电柜分别引出至现场二级配电箱回路。现场采用“三相五线”制TN-S接零保护系统,分级配电,逐级设置漏电保护。

6.1电缆电线设置

6.1.1、矩形洞出入口内的电缆电线敷设必须采用绝缘导线或电缆;

6.1.2、洞内电缆电线敷设采用角钢和瓷瓶(绝缘措施)、绝缘子固定进行敷设,各个大桥施工现场采用地埋电缆敷设;

6.1.3、瓷瓶固定导线时,导线间距不应小于100mm,瓷瓶间距不应大于1.5m;

6.1.4、电缆电线敷设时必须有短路保护和过载保护:

10

6.1.5、采用断路器做短路保护时,其瞬动过流脱扣器脱扣电流整定值应小于线路末端单相短路电流;

6.1.6、采用断路器做过载保护时,绝缘导线长期连续负荷允许载流量不应小于断路器延时过流脱扣器 脱扣电流整定值的1.2倍。

第7章 保护接零、接地与防雷要求

《施工现场临时用电安全技术规范》(JGJ46-2005)中规定:“在施工现场专用变压器的供电的TN-S接零保护系统中,电气设备的金属外壳必须与保护零线连接。保护零线应由工作接地线、配电室(总配电箱)电源零线或总漏电保护器电源侧零线引出”。

如下图:

“当施工现场与外电线路共用同一供电系统时,电气设备的接地\\接零保护应与原系统保持一致.不得一部分设备做保护接零,另一部分设备做保护接地.

11

采用TN系统做保护接零时,工作零线(N线)必须通过总漏电保护器 ,保护零线(PE线)必须由电源进线零线重复接地处或总漏电保护器电源侧零线处,引出形成TN-S 接零保护系统”.

7.1接零保护的定义

接零保护是指施工现场电气设备正常情况下不带电的金属外壳和机械设备的金属构架与保护零线连接。

7.2接零保护的优点

中性点直接接地的低压电力系统按其电气设备的保护方式,将电气设备正常情况下不带电的金属外壳作接零保护的TN系统,其又分为两种形式:工作零线(N线)与保护零线(PE线)独立分开设置的TN-S系统,称三相五线制接零保护系统。

TN-S系统具有最高的安全性和可靠性。该系统工作零线与保护零线分开设置,完全独立,当设备正常运行或出现三相负荷不平衡时,工作零线中有电流经过,保护零线中无电流经过,从而保证电气设备的金属外壳不会出现电压,与电力系统的工作接地点等电位;当电气设备发生对地短路或漏电故障时,设备外壳带电,保护零线中有故障电流经过,形成回路,由于该回路阻抗小,短路电流大,促使漏电保护和短路保护装置迅速反应切断电源,起到保护作用。 施工现场重复接地连接示意图:

施工现场重复接地材料(镀锌圆钢、镀锌扁铁):

12

7.3接零保护的实施:保护零线的要求和设置

7.3.1、保护零线必须采用黄绿双色绝缘电线,在任何情况下不准使用黄绿双色线作负荷线。

7.3.2、保护零线的截面积不得小于相线的一半,应与工作零线的截面积相同。当其架空敷设间距大于12m时,保护零线必须选择不小于10的绝缘铜线或不小于16mm2的绝缘铝线;当其与电气设备连接时,保护零线应为不小于2.5mm2的绝缘多股铜线。

PE线截面与相线截面的关系:

相线芯线截面S(mm2) S≤16 167.3.4、保护零线不得装设开关、熔断器、漏电保护器等隔离装置或保护装置。

7.3.5、正常情况下,保护零线应连接到下列电气设备不带电的外露导电部分:

①电机、变压器、电器、照明器具、手持电动工具的金属外壳; ②电气设备传动装置的金属部件; ③配电屏与控制屏的金属框架;

④室内、外配电装置的金属构架及靠近带电部分的金属围栏和金

13

属门;

⑤电力线路的金属保护管、敷线的钢索;

7.3.6、对产生振动的设备,其保护零线的连接点应不少于两处。

7.4关于重复接地的合理设置

重复接地能有效降低故障点的对地电压,缩短故障的持续时间,减轻了保护零线断线后的危险,因此《施工现场临时用电安全技术规范》要求:TN系统中的保护零线除必须在配电室或总配电箱处做重复接地外,还必须在配电系统的中间和末端处做重复接地。

在TN系统中,保护零线每一处重复接地装置的接地电阻值不应大于10Ω。在工作接地电阻值允许达到10Ω的电力系统中,所有重复接地的等效电阻值不应大于10Ω。

第8章 临时用电施工技术要求

本工程严格按照《施工现场临时用电安全技术规范》(JGJ46—2005)和《建筑工程施工现场供电安全规范》(GB50144-93)的有关规定进行施工,采用TN-S系统供电。

本工程使用的现场配电箱应符合6天津市有关安全用电管理规定。施工现场配电箱必须采用合格生产厂家生产的产品,严禁私拆改装。工地所有配电箱门上都要标明电箱的名称、所控制的各线路称谓、编号、用途等,并标有系统图,必须加锁。

14

二级配电箱配置

8.1变压器及配电线路的布置

8.1.1、本工程的临时供电线路采用放射式和树干式相结合的供电方式。

8.1.2、变压器设置在引入电源的安全区,变压器设在用电集中的地方,或者布置在现场边缘高压接入处,四周应设有明显的标志牌和护栏。

8.1.3、线路宜在路边布置,距建筑物应大于1.5米,线路不应妨碍交通和机械施工、进场、拆卸、吊装等,线路应避开堆放、临时设施、基础及后期工程的地方,注意按规范接线和用电使用上的安全性。

8.1.4、现场采用三相五线制系统。机械设备所有不带电的金属外壳均应作可靠接地,接地电阻小于10Ω。

15

8.2临时供电

施工临时供电从业主提供的供电接口引入施工现场,在天津市电力部门许可的位置以及场地内合理的位置修建箱式变压器,采用三相五线制接线,在变压器输出端设总动力配电电箱。用电缆接入工地配电箱。施工现场供电线路采用架空电缆和部分埋设电缆,埋设电缆均采用穿钢管以及其它保护措施,以保护电缆。

8.3场地用电的安装工艺与要求

8.3.1、在每个用电点的配电箱周围应打L50*5,L=2.5米的镀锌角钢(镀锌圆钢)接地级三根间隔距离为5米,全部埋入地下70cm,用25*4镀锌扁铁与接地级焊接后,引至配电箱PE端子排上,使角钢接地级与施工箱式变压器低压侧的零线构成重复接地系统,接地电阻不大于10Ω,各用电设备的金属外壳用专用接地软铜线连接。

8.3.2、电缆敷设方法采用埋地敷设,过路处需要穿钢管暗埋敷设。

8.3.3、从配电箱馈出的配电箱其中一路的开关载流量和短路电流需于用电设备的容量相匹配,设备在受电使用前应检验电开关的动作是否正确。

8.3.4、高压电缆送电前,必须进行电气实验,验收合格后方可送电。

16

8.4施工照明

8.4.1、施工现场照明应采用高光效、长寿命的照明光源。工作场所不得只装设局部照明,对于需要大面积照明的场所,应采用高压汞灯、高压钠灯,灯头与易燃物的净距离不小于0.5m。流动性高压汞灯、高压钠灯采用金属支架安装时,支架应稳固,灯具与金属支架之间必须用不小于0.2m的绝缘材料隔离。灯具的金属外壳必须做保护接零,手持部分必须采用可靠的绝缘措施。

8.4.2、施工照明灯具露天装设时,应采用防水式灯具,距地面高度不得低于3m。工作棚、场地的照明灯具,可分路控制,每路照明支线上连接灯数不得超过10盏,若超过10盏时,每个灯具上应装设熔断器。

8.4.3、一般施工场所宜选用额定电压为220V的照明灯具,不得使用带开关的灯头,应选用螺口灯头。相线接在与中心触头相连的一端,零线接在与螺纹口相连的一端。灯头的绝缘外壳不得有损伤和漏电,照明灯具的金属外壳必须做保护接零。单项回路的照明开关箱内必须装设漏电保护开关。

8.4.4、现场局部照明用的工作灯,在潮湿的作业环境,照明电源电压应不大于36V。在特别潮湿,导电良好的地面工作的照明灯具,其电源电压不得大于l2V。工作手灯应用胶把和网罩保护。

8.4.5、 36V的照明变压器,必须使用双绕组型,二次线圈、铁芯、金属外壳必须有可靠保护接零。一、二次侧应分别装设熔断器,一次线长度不应超过3m。照明变压器必须有防雨、防砸措施。

17

8.4.6、照明线路不得拴在金属脚手架、龙门架上,严禁在地面上乱拉、乱拖。灯具需要安装在金属脚手架、龙门架上时,线路和灯具必须用绝缘物与其隔离开,且距离工作面高度在3m以上。控制刀闸应配有熔断器和防雨措施。

8.4.7、施工现场的照明灯具应采用分组控制或单灯控制。

8.5施工用电线路

电缆干线应采用埋地或架空敷设,严禁沿地面明敷设,并应避免机械损伤和介质腐蚀。

8.5.1、电缆在室外直接埋地敷设时,必须按电缆埋设图敷设,并应砌砖槽防护,埋设深度不得小于0.7m。

8.5.2、电缆的上下各均匀铺设不小于5cm厚的细砂,上盖电缆盖板或白砂砖作为电缆的保护层。

8.5.3、地面上应有埋设电缆的标志,并应有专人负责管理。不得将物料堆放在电缆埋设的上方。

8.5.4、有接头的电缆不准埋在地下,接头处应露出地面,并配

18

电缆埋设,垫沙、盖砖

有电缆接线盒 (箱)。电缆接线盒 (箱)应防雨、防尘、防机械损伤,并远离易燃、易爆、易腐蚀场所。

8.5.5、电缆穿越建筑物、构筑物、道路、易受机械损伤的场所必须加设防护套管。

8.5.6、在施建筑的临时电缆配电,必须采用电缆埋地引入。电缆垂直敷设时,位置应充分利用竖井、垂直孔洞。接触、跨过金属部分必须做好绝缘措施:使用绝缘塑料垫、瓷瓶进行线路固定,其固定点每3米不得少于一处。水平敷设应沿墙或孔洞在固定支架上利用瓷瓶做好绝缘处理固定,最大弧垂距离地面不得小于1.8m。

8.6配电箱的设置

现场临时配电箱、开关箱应采用冷轧钢板和绝缘材料制作,钢板厚度应为1.2mm~2.0mm,其中开关箱箱体钢板厚度不得小于1.2mm,配电箱箱体厚度不得小于1.5mm,箱体表面应做防腐处理。

配电箱、开关箱应装设端正、牢固。固定式配电箱、开关箱的中心点与地面的垂直距离应为1.4~1.6m。移动式配电箱、开关箱应装设在坚固、稳定的支架上。其中心点与地面的垂直距离宜为0.8~1.6m。

配电箱的电器安装板上必须分设N线端子板和PE线端子板。N线端子板必须与金属电器安装板绝缘;PE线端子板必须与金属电器安装板做电气连接。进出线中的N线必须通过N线端子板连接;PE线必须通过PE线端子板连接。

配电箱根据其用途和功能的不同,一般可分为三级:

8.6.1、总配电箱 (又称固定式配电箱)。一级配电箱用符号 “A”

19

表示。总配电箱是控制施工现场全部供电的集中点,应设置在靠近电源地区。电源由施工现场用电变压器低压侧引出的电缆线接入,并装设电流互感器、有功电度表、无功电度表、电流表、电压表及总开关、分开关。总配电箱内的开关均应采用自动空气开关 (或漏电保护开关)。引入、引出线应穿管并有防水弯。

8.6.2、分配电箱 (又称移动式配电箱)。分配电箱用符号 “B”表示。其中1、2、3表示序号。分配电箱是总配电箱的一个分支,控制施工现场某个范围的用电集中点,应设在用电设备负荷相对集中的地区。箱内应设总开关和分开关。总开关应采用自动空气开关,分开关可采用漏电开关或刀闸开关并配备熔断器。

8.6.3、开关箱直接控制用电设备。开关箱与所控制的固定式用电设备的水平距离不得大于3m,与分配电箱的距离不得大于30m。开关箱内安装漏电开关、熔断器及插座。电源线采用橡套软电缆线,从分配电箱引出,接入开关箱上闸口。

8.6.4、配电箱、开关箱内的连线必须采用铜芯绝缘导线,相线L1(A)、L2(B)、L3(C) 相序的绝缘颜色依次为黄、绿、红色;N线的绝缘颜色为淡蓝色;PE线的绝缘颜色为绿/黄双色。任何情况下上述颜色标记严禁混用和互相代用。配电箱、开关箱的金属箱体、金属电器安装板以及电器正常不带电的金属底座、外壳等必须通过PE线端子板与PE线做电气连接,金属门与金属箱体必须通过采用编制软铜线做电气连接。

8.6.5、 配电箱和开关箱的进出线口,应设在箱体的下面,并加

20

护套保护。进、出线应分路成束,不得承受外力,并做好防水弯。导线束不得与箱体进、出线口直接接触。

8.6.6、配电箱内的开关及仪表等电器排列整齐,配线绝缘良好,绑扎成束。配电箱的操作盘面不得有带电体明露。箱内应整洁,不得放置工具等杂物,箱门应有锁,并用红色油漆喷上警示标语和危险标志,喷写配电箱分类编号。箱内应设有线路图。

8.6.7、配电箱周围2m内不得堆放杂物。电工应经常巡视检查开关、熔断器的接点处是否过热。各接点是否牢固,配线绝缘有无破损,仪表指示是否正常等。发现隐患立即排除。配电箱应经常清扫除尘。

8.6.8、每台用电设备应有各自专用的开关箱,必须实行“一机一闸一漏一箱”制,严禁同一个开关电器直接控制二台及二台以上用电设备 (含插座)。

8.6.9、两级漏电保护。总配电箱和开关箱中两级漏电保护器的额定漏电动作电流和额定漏电动作时应合理配合,使之具有分级、分段保护的功能。

8.6.10、施工现场的漏电保护开关不得随意拆卸和调换零部件,以免改变原有技术参数。并应经常检查试验,发现异常,必须立即查明原因,严禁带病使用。

8.7电缆的安装架设

8.7.1、 架设电缆轴的地面必须平实。支架必须采用有底平面的专用支架,不得用千斤顶等代替。敷设电缆必须按安全技术措施交底内容执行,并设专人指挥。

21

8.7.2 、人力拉引电缆时,力量要均匀,速度应平稳,不得猛拉猛跑。看轴人员不得站在电缆轴前方。敷设电缆时,处于拐角的人员,必须站在电缆弯曲半径的外侧。过管处的人员必须做到:送电缆时手不可离管口太近;迎电缆时,眼及身体严禁直对管口。

8.7.3、竖直敷设电缆,必须有预防电缆失控下溜的安全措施。电缆放完后,应立即固定、卡牢。

8.7.4、人工滚运电缆时,推轴人员不得站在电缆前方,两则人员所站位置不得超过缆轴中心。电缆上、下坡时,应采用在电缆轴中心孔穿铁管,在铁管上拴绳拉放的方法,平稳、缓慢进行。电缆停顿时,将绳拉紧,及时“打掩”制动。人力滚动电缆路面坡度不宜超过15°。

8.7.5、汽车运输电缆时,电缆应尽量放在车头前方 (跟车人员必须站在电缆后面),并用钢丝绳固定。

8.7.6、挖电缆沟时,应根据土质和深度情况按规定放坡。在交通道路附近地区施工电缆沟时,应设置栏杆和标志牌,夜间设红色标志灯。

8.7.7、在隧道内或者结构内部敷设电缆时,临时照明的电压不得大于36V。施工前应将地面进行清理,积水排净。

8.8施工现场变配电维修以及注意事项

8.8.1、 现场变配电高压设备,不论带电与否,单人值班严禁跨越遮栏和从事修理工作。

8.8.2、 高压带电区域内部分停电工作时,人体与带电部分必须

22

保持安全距离,并应有人监护。

8.8.3 、在变配电室内,外高压部分及线路工作时,应按顺序进行。停电、验电、悬挂地线,操作手柄应上锁或挂标示牌。

8.8.4 、验电时必须戴绝缘手套,按电压等级使用验电器。在设备两侧各相或线路各相分别验电。验明设备或线路确实无电后,即将检修设备或线路做短路接地。

8.8.5、 装设接地线,应由两人进行。先接接地端,后接导体端,拆除时顺序相反。拆接时均应穿戴绝缘防护用品。设备或线路检修完毕,必须全面检查无误后,方可拆除接地线。

8.8.6 、接地线应使用截面不小于25mm²的多股软裸铜芯线和专用线夹。严禁使用缠绕的方法进行接地和短路。

8.8.7 、拉、合高压开关,应戴绝缘手套。雨天室外操作时,除穿戴绝缘防护用品外,应专人监护。严禁带负荷拉、合开关。

8.8.8、 电气设备的金属外壳必须接地或接零。同一供电系统不允许一部分设备采用接零,另一部分采用接地保护。

第9章 安全用电措施

根据JGJ46-2005《施工现场临时用电安全技术规范》规范标准编制。

一、本项目《临时用电施工组织设计》,采用TN—S三相五线制供电系统对现场进行供电,照明线路与动力线路严格分开并保持安全距离,作业面照明采用36V以下的安全电压,安全电压变压器设在干

23

燥、安全处。作业面采用橡胶软电缆接线。

二、供电系统安装完成后必须经过项目安全总监和公司安全部门验收合格后方可使用。

三、所有施工人员掌握安全用电的基本知识和所用设备性能,用电人员各自保护好设备的负荷线、接地线和开关,发现问题及时找电工解决,严禁非专业电气操作人员乱动电器设备。

9.1电工职责

9.1.1、电工作业必须经专业安全技术培训,考试合格,持《中华人民共和国特种作业操作证》方可持证上岗工作。非电工严禁进行电气作业。

9.1.2、电工接受施工现场暂设电气安装任务后,必须认真领会落实临时用电安全施工组织设计 (施工方案)和安全技术措施交底的内容,施工用电线路架设必须按施工图规定进行,凡临时用电使用超过六个月 (含六个月)以上的,应按正式线路架设。改变安全施工组织设计规定,必须经原审批单位领导同意签字,未经同意不得改变。

9.1.3、电工作业时,必须穿绝缘鞋、戴绝缘手套,酒后不准操作。

9.1.4、所有绝缘、检测工具应妥善保管,严禁他用,并应定期检查、校验。保证正确可靠接地或接零。所有接地或接零处,必须保证可靠电气连接。保护零线PE必须采用绿/黄双色线,严禁与相线、工作零线相混用。

9.1.5、 电气设备的设置、安装、防护、使用、维修必须符合《施

24

工现场临时用电安全技术规范》(JGJ46—2005)。

9.1.6、定期和不定期对临时用电工程的接地、设备绝缘和漏电保护开关进行检测、维修,发现隐患及时消除,并建立检测维修记录。

9.2安全用电技术措施

9.2.1、保护接地

是指将电气设备不带电的金属外壳与接地极之间做可靠的电气连接。它的作用是当电气设备的金属外壳带电时,如果人体触及此外壳时,由于人体的电阻远大于接地体电阻,则大部分电流经接地体流入大地,而流经入人体的电流很小。这时只要适当控制接地电阻(一般不大于4Ω),就可减少触电事故发生。

9.2.2、保护接零

在电源中性点直接接地的低压电力系统中,将用电设备的金属外壳与供电系统中的零线或专用零线直接做电气连接,称为保护接零。它的作用是当电气设备的金属外壳带电时,短路电流经零线而成闭合电路,使其变成单相短路故障,因零线的阻抗很小,所以短路电流很大,一般大于额定电流的几倍甚至几十倍,这样大的单相短路将使保护装置迅速而准确的动作,切断事故电源,保证人身安全。

TN-S供电系统。它是把工作零线N和专用保护线PE.在供电电源处严格分开的供电系统,也称三相五线制。它的优点是专用保护线上无电流,此线专门承接故障电流,确保其保护装置动作。应该特别指出,PE线不许断线。

不管采用保护接地还是保护接零,必须注意:在同一系统中不允

25

许对一部分设备采取接地,对另一部分采取接零。因为在同一系统中,如果有的设备采取接地,有的设备采取接零,则当采取接地的设备发生碰壳时,零线电位将升高,而使所有接零的设备外壳都带上危险的电压。

9.2.3、设置漏电保护器

1)、施工现场的总配电箱和开关箱应至少设置两级漏电保护器,而且两级漏电保护器的额定漏电动作电流和额定漏电动作时间应作合理配合,使之具有分级保护的功能。

2)、开关箱中必须设置漏电保护器,施工现场所有用电设备,除作保护接零外,必须在设备负荷线的首端处安装漏电保护器。

3)、漏电保护器应装设在配电箱电源隔离开关的负荷侧和开关箱电源隔离开关的负荷侧。

4)、漏电保护器的选择应符合国标GB6829—86《漏电电流动作保护器(剩余电流动作保护器)》的要求,开关箱内的漏电保护器其额定漏电动作电流应不大于30mA,额定漏电动作时间应小于0.1s。使用潮湿和有腐蚀介质场所的漏电保护器应采用防溅型产品。其额定漏电动作电流应不大于15mA,额定漏电动作时间应小于0.1s。

9.2.4、安全电压

安全电压指不戴任何防护设备,接触时对人体各部位不造成任何损害的电压。我国国家标准GB3805—83《安全电压》规定:当电气设备采用了超过24V时,必须采取防直接接触带电体的保护措施。

对下列特殊场所应使用安全电压照明器:隧道、人防工程、有高

26

温、导电灰尘或灯具离地面高度低于2.m等场所的照明,电源电压应不大于36V。

9.2.5、 电气设备的设置要求

1)、配电系统应设置室内总配电屏和室外分配电箱或设置室外总配电箱和分配电箱,实行分级配电。

2)、动力配电箱与照明配电箱宜分别设置,如合置在同一配电箱内,动力和照明线路应分路设置,照明线路接线宜接在动力开关的上侧。

3)、开关箱应由末级分配电箱配电。开关箱内应一机一闸,每台用电设备应有自己的开关箱,严禁用一个开关电器直接控制两台及以上的用电设备。

4)、总配电箱应设在靠近电源的地方,分配电箱应装设在用电设备或负荷相对集中的地区。分配电箱与开关箱的距离不得超过30m,开关箱与其控制的固定式用电设备的水平距离不宜超过3m。

5)、配电箱、开关箱应装设在干燥、通风及常温场所。不得装设在有严重损伤作用的瓦斯、烟气、蒸汽、液体及其他有害介质中。也不得装设在易受外来固体物撞击、强烈振动、液体浸溅及热源烘烤的场所。配电箱、开关箱周围应有足够两人同时工作的空间,其周围不得堆放任何有碍操作、维修的物品。

6)、配电箱、开关箱安装要端正、牢固,移动式的箱体应装设在坚固的支架上。固定式配电箱、开关箱配电箱、开关箱应装设端正、牢固。固定式配电箱、开关箱的中心点与地面的垂直距离应为1.4~

27

1.6m。移动式配电箱、开关箱应装设在坚固、稳定的支架上。其中心点与地面的垂直距离宜为0.8~1.6m。

7)、配电箱、开关箱中导线的进线口和出线口应设在箱体下底面,严禁设在箱体的上顶面、侧面、后面或箱门处。

9.2.6、 电气设备的安装

1)、配电箱内的电器应首先安装在金属或非木质的绝缘电器安装板上,然后整体紧固在配电箱箱体内,金属板与配电箱体应作电气连接。

2)、配电箱、开关箱内的各种电器应按规定的位置紧固在安装板上,不得歪斜和松动。并且电器设备之间、设备与板四周的距离应符合有关工艺标准的要求。

3)、配电箱、开关箱内的工作零线应通过接线端子板连接,并应与保护零线接线端子板分设.

4)、配电箱、开关箱内的连接线应采用绝缘导线,导线的型号及截面应严格执行临电图纸的标示截面。各种仪表之间的连接线应使用截面不小于2.5mm2的绝缘铜芯导线,导线接头不得松动,不得有外露带电部分。

5)、各种箱体的金属构架、金属箱体,金属电器安装板以及箱内电器的正常不带电的金属底座、外壳等必须做保护接零,保护零线应经过接线端子板连接。

6)、配电箱后面的排线需排列整齐,绑扎成束,并用卡钉固定在盘板上,盘后引出及引入的导线应留出适当余度,以便检修。

28

7)、导线剥削处不应伤线芯过长,导线压头应牢固可靠,多股导线不应盘圈压接,应加装压线端子(有压线孔著除外)。如必须穿孔用顶丝压接时,多股线应刷锡后再压接,不得减少导线股数。

9.2.7、 电气设备的外电防护

1)、在建工程不得在高、低压线路下方施工,高低压线路下方,不得搭设作业棚、建造生活设施,或堆放构件、架具、材料及其他杂物。

2)、施工时各种架具的外侧边缘与外电架空线路的边线之间必须保持安全操作距离。当外电线路的电压为1kV以下时,其最小安全操作距离为4m;当外电架空线路的电压为1~lOkV时,其最小安全操作距离为6m;当外电架空线路的电压为35~lOkV时,其最小安全操作距离为8m。上下脚手架的斜道严禁搭设在有外电线路的一侧。旋转臂架式起重机的任何部位或被吊物边缘与lOkV以下的架空线路边线最小水平距离不得小于2m。

3)、施工现场的机动车道与外电架空线路交叉时,架空线路的最低点与路面的最小垂直距离应符合以下要求:外电线路电压为1kV以下时,最小垂直距离为6m;外电线路电压为l~35kV时;最小垂直距离为7m。

4)、对于达不到最小安全距离时,施工现场必须采取保护措施,可以增设屏障、遮栏、围栏或保护网,并要悬挂醒目的警告标志牌。在架设防护设施时应有电气工程技术人员或专职安全人员负责监护。

5)、对于既不能达到最小安全距离,又无法搭设防护措施的施工

29

现场,施工单位必须与有关部协商,采取停电、迁移外电线或改变工程位置等措施,否则不得施工。

9.2.8、 电气设备的操作与维修人员必须符合以下要求 1)、施工现场内临时用电的施工和维修必须由经过培训后取得上岗证书的专业电工完成,电工的等级应同工程的难易程度和技术复杂性相适应,初级电工不允许进行中、高级电工的作业。

2)、各类用电人员应做到:

(a)掌握安全用电基本知识和所用设备的性能;

(b)使用设备前必须按规定穿戴和配备好相应的劳动防护用品;并检查电气装置和保护设施是否完好。严禁设备带“病”运转;

(c)停用的设备必须拉闸断电,锁好开关箱;

(d)负责保护所用设备的负荷线、保护零线和开关箱。发现问题,及时报告解决;

(e)搬迁或移动用电设备,必须经电工切断电源并作妥善处理后进行。

9.2.9、 电气设备的使用与维护

1)、施工现场的所有配电箱、开关箱应每月进行一次检查和维修。检查、维修人员必须是专业电工。

2)、检查、维修配电箱、开关箱时,必须将其前一级相应的电源开关分闸断电,并悬挂停电标志牌,严禁带电作业。

3)、配电箱内盘面上应标明各回路的名称、用途、同时要作出分路标记。

30

4)、总、分配电箱门应配锁,配电箱和开关箱应指定专人负责。施工现场停止作业1h以上时,应将动力开关箱断电上锁。

5)、各种电气箱内不允许放置任何杂物,并应保持清洁。箱内不得挂接其他临时用电设备。

9.2.10、施工现场的电缆线路

1)、电缆线路应采用穿管埋地或沿墙、电杆架空敷设,严禁沿地面明设。

2)、电缆在室外直接埋地敷设的深度应不小于0.7m,并应在电缆上下各均匀铺设不小于50mm厚的细砂,然后覆盖砖等硬质保护层。

3)、橡皮电缆沿墙或电杆敷设时应用绝缘子固定,严禁使用金属裸线作绑扎。固定点间的距离应保证橡皮电缆能承受自重所带的荷重。橡皮电缆的最大弧垂距地不得小于2.5m。

4)、电缆的接头应牢固可靠,绝缘包扎后的接头不能降低原来的绝缘强度,并不得承受张力。

9.2.11、室内导线的敷设及照明装置

1)、室内配线必须采用绝缘铜线或绝缘铝线,采用瓷瓶、瓷夹或塑料夹敷设,距地面高度不得小于2.5m。

2)、进户线在室外处要用绝缘子固定,进户线过墙应穿套管,距地面应大于2.5m,室外要做防水弯头。

3)、室内配线所用导线截面应按图纸要求施工,铜线截面不得小于1.5mm2。

4)、金属外壳的灯具外壳必须作保护接零,所用配件均应使用镀

31

锌件。

5)、室外灯具距地面不得小于3m,室内灯具不得低于2.5m。插座接线时应符合规范要求。

6)、螺口灯头及接线应符合下列要求:

(a)相线接在与中心触头相连的一端,零线接在与螺纹口相连的一端。

(b)灯头的绝缘外壳不得有损伤和漏电。

7)、各种用电设备、灯具的相线必须经开头控制,不得将相线直接引入灯具。

8)、暂设室内的照明灯具应优先选用拉线开关,拉线开关距地面高度为2~3m,与门口的水平距离为0.1~0.2m,拉线出口应向下。

9)、严禁将插座与搬把开关靠近装设;严禁在床上设开关。

第10章 电气线路的火灾原因及预防措施

电气线路发生火灾,主要是由于线路的短路、过载或接触电阻过大等原因,产生电火花、电弧或引起电线、电缆过热,从而造成火灾。 10.1短路

10.1.1、电气线路发生短路的主要原因有:

1)、使用绝缘电线、电缆时,没有按具体环境选用,使绝缘受高温、潮湿或腐蚀等作用,失去了绝缘能力。 2)、绝缘层陈旧老化或受损,使线芯裸露。 3)、电源过电压,使电线绝缘被击穿。

32

4)、安装、修理人员接错线路,或带电作业时造成人为碰线短路。 5)、电线机械强度不够,导致电线断落接触大地,或断落在另一根电线上。

6)、不按规定要求私拉乱接,管理不善,维护不当造成短路。 10.1.2、防止短路的措施

1)、导线与导线、墙壁、顶棚、金属构件之间,以及固定导线的绝缘子、瓷瓶之间,应有一定的距离。

2)、距地面2m以及穿过墙壁的导线,均应有保护绝缘的措施,以防损伤。

3)、绝缘导线切忌用铁丝捆扎和铁钉搭挂。 4)、定期对绝缘电阻进行测定。 5)、安装线路应为持证电工安装。 6)、安装相应的保险器或自动开关。

10.2过载(超负荷)

10.2.1、发生过载的主要原因有:

1)、导线截面积选择不当,实际负载超过了导线的安全载流量。 2)、在线路中接入了过多或功率过大的电气设备,超过了配电线路的负载能力。

10.2.2、防止过载的措施 1)、合理选用导线截面。

2)、切忌乱拉电线和过多的接入负载。 3)、定期检查线路负载与设备增减情况。

33

4)、安装相应的保险或自动开关。 10.3接触电阻过大

10.3.1、发生接触电阻过大的主要原因有:

1)、安装质量差,造成导线与导线、导线与电气设备连接点连接不牢。

2)、导线的连接处沾有杂质,如氧化层、泥土、油污等。 3)、连接点由于长期震动或冷热变化,使接头松动。线路接通电源之后,电流通过电线、接头和设备就会发热,这是正常现象。接头做得好,接触电阻不大,连接点的发热量就小,可以保持正常温度。如果接头接得不好,接触电阻就会增大,同时产生的热量也就多。在一定电流下,电阻越大发热量就越多。因此,有较大接触电阻的线段就会强烈发热,使温度急剧升高引起导线绝缘层的燃烧,以致引起附近电线上的粉尘、纤维等物质燃烧起来,若处理不当就会引起火灾。如电动机振动时,就有可能使接头松动,产生接触电阻过大,因局部温度升高引燃发生火灾。

10.3.2防止接触电阻过大的措施:

1)、应尽量减少不必要的接头,对于必不可少的接头,必须紧密结合,牢固可靠。

2)、铜芯导线采用绞接时,应进行锡焊处理,采用焊接和压接。 3)、经常进行检查测试,发现问题,及时处理。

为了防止或减少配电线路事故的发生,必须按照电气安全技术规程进行设计,安装使用时要严格遵守岗位责任制和安全操作规程,加

34

强维护管理,及时消除隐患,保障用电安全。

第11章 触电事故的应急预案

11.1防触电事故的措施:

11.1.1、施工用电实行三级漏电配电,施工电缆线按规定架空铺设;

11.1.2、开关箱内的漏电保护器具额定漏电电流应不小于30mA,额定漏电应不大于15mA,额定漏电动作时间不能大于0.1s;

11.1.3、保护零线按规定作好重复接地; 11.1.4、洞内施工照明采用36V低压照明线路;

11.1.5、气焊作业双线到位,氧气、乙炔之间留不小于5m的安全距离;

11.1.6、非电工人员不得拆改电器、电源,电工人员必须执证上岗,一般职工也应了解用电常识及有关安全规程;

11.1.7、电工定期对施工现场用电设备进行检查,及时发现和排除电气事故隐患,尤其在雨季;

11.1.8、电器设备投入使用前检查绝缘电阻必须合格,设备裸露带电部分必须有防护、保护接零或接地必须可靠、保护装置必须符合要求。对于使用中的电器设备,应定期测定其绝缘电阻,对于各种接地装置,应定期测定其接地电阻;

11.1.9、为了便于检查,各工程队应对重要的设备单独建立资料档案,每次检修和实验记录应作为资料保存,以便核对。

35

11.2触电事故的应急预案

有人触电时,抢救者首先要立刻断开近处电源(拉闸、拔插头),如触电距开关太远,用电工绝缘钳或干燥木柄铁锹、斧子等切断电线断开电源,或用绝缘物如木板、木棍等不导电材料拉开触电者或者挑开电线,使之脱离电源,切忌直接用手或金属材料及潮湿物件直接去拉电线和触电的人,以防止解救的人再次触电。

触电人脱离电源后,如果触电人神志清醒,但有些心慌、四肢麻木、全身无力;或者触电人在触电过程中曾一度昏迷,但已清醒过来,应使触电人安静休息,不要走动,严密观察,必要时送医院诊治。

触电人已失去知觉,但心脏还在跳动,还有呼吸,应使触电人在空气清新的地方舒适、安静地平躺,解开妨碍呼吸的衣扣、腰带,若天气寒冷要注意保持体温,并迅速请医生(或打120)到现场诊治。

如果触电人已失去知觉、呼吸停止,但心脏还在跳动,尽快把他仰面放平进行人工呼吸。

如果触电人呼吸和心脏跳动完全停止,应立即进行人工呼吸和心脏胸外按压急救。

抢救过程中尽快将事故情况向项目部应急处理小组汇报,应急事件处理小组到达事故现场指挥抢救,根据事故情况大小向上级主管部门、安检、公安部门报告并按规定填写安全事故报告书。

36

第12章 冬雨季安全用电措施

12.1电气安装工程

12.1.1、电气线管,器具要妥善保管,置放位置要高,可加垫,必要时应遮掩。

12.1.2、对潮湿闷热的环境,可安装通风机或电扇驱潮保证其绝缘,不影响其使用性能,电缆、电线要检查封口,尽量置于结构通道内,没有条件的情况下,要有遮盖措施,并将端头包裹严密。

12.1.3、暴露在室外的电气管线在进入箱、盒时要作防水弯。 12.1.4、对施工过程中电线管口,易进水处要进行封堵。对于地下坑、井中的泵机要有遮盖。坑、井要作排水,必要时设专人看护。

12.1.5、变压器、电动机不要在雨天拆装检验,如要检验应在通风、干燥的室内进行。

12.1.6、电焊机、电动机工具等用电设备的漏电保护装置要可靠。焊机、电动装置、设备应置于室内或遮掩,焊机手把线及电动设备的电源线不能拖地、破皮。雨期期间要加强电焊条烘干的管理,焊条烘干后要有保温筒,防止受潮,现场存放期间不宜过长。

12.1.7、采取晴雨结合施工,晴天施工条件好,多完成室外作业,雨天多完成室内作业。

12.1.8、所有电动设备外壳必须与PE线做电气连接。 12.1.9、在雨期使用电器设备的操作者,要穿绝缘鞋,戴绝缘手套,防止触电。

37

12.2施工机械设备安全使用

12.2.1、施工现场对进入现场的机械设备实行统一管理,保证机械设备状况完好,确保雨期安全使用。

12.2.2、各项目经理部协助机械管理班组对工地使用的所有机械、电器设备进行一次全面的安全检查,认真做好防雨工作,确保雨期使用安全。

12.2.3、做好各种露天使用的电器设备、电闸箱的防雨、防潮、防砸等措施。电器设备、电闸箱、机械设备配备完好的防护盖,放置在现场干燥较高的位置,并用木方垫起,不能放在坑洼处。

12.2.4、经常检查施工现场电器设备的接零、接地等保护设施的可靠性及灵敏性。

12.2.5、临时搭建的电线、电缆对有破损、腐蚀严重及达不到绝缘要求的坚决予以更换。

12.2.6、临时搭建的电线、电缆严禁拖地明设,并应避免机械损伤,对于无法埋地或架空的部分,必须使用铠装电缆并外加“∩”形保护盒或穿管敷设。

12.2.7、在露天及潮湿场所或金属构架上作业,必须使用Ⅱ类手持电动工具,并装备漏电保护装置,严禁使用Ⅰ类手持电动工具。

12.2.8、使用行灯照明,其电源电压不得超过36伏,灯体与手柄应牢固绝缘良好,在潮湿场所内工作时,行灯电压不得超过12伏。

12.2.9、对机械的电气系统罩起来,防止雨水进入。雨后使用应进行全面检查,确认正常后方可投入使用。

38

12.2.10、混凝土输送泵应安装在坚实支承力强的地面,四周排水通畅并且不得有积水,工作场所应搭设防雨、防晒、防砸等保护棚,且要通风好。

12.2.11、雨期长期停用的机械设备,要认真做好防雨工作。 各项目及专业公司应组织施工管理人员学习有关雨期施工的文件和措施,提高质量、安全意识,严格按国家规范、规程、规定施工,不得违章指挥、违章作业,要加强天气预报的收听,做好雨天防范措施。

严格执行《施工现场临时用电安全技术规范》(JGJ46-2005)。 12.3.1、机械设备等要经常检查,及时检修维护,尤其是大风暴雨后,应先检查,维修后方可使用,每日作业完毕,应将拉闸断电。

12.3.2、施工现场内机械设备,在相邻建筑物、构筑物的防雷装置的保护范围以外,必须安装防雷装置,施工现场内所有的防雷装置的冲击接地电阻值不得大于10Ω,高大机械的防雷装置应单独设置,不应借用架子或建筑物的防雷装置,机械设备上的避雷针长度应为1-2m。

12.3.3、基坑边严禁堆放物品,防止塌方伤人。

12.3.4、易燃、易爆物品要妥善存放、保管、防止受潮,变质起火、爆炸。仓库及堆放场地要有灭火设施。

12.3.5、施工作业时,易产生可燃、有毒气体时,应在保证施工作业外面通风良好,或配强制通风设施。

12.3.6、要经常检查灭火设施是否有效,消防器材是否齐全。

39

12.3.7、施工中明火作业必须配备固定的看火人员和灭火器材,必须办用火手续,方可按北京市有关规定进行施工作业。

12.3.8、露天的机电设备要加强防雨罩或搭设防雨棚,现场使用的一切电动工具、机电设备均应安装漏电保护器,并保护好接地、接零装置,下班后要切断各种机具设备电源。

12.3.9、照明变压器应有防雨,防潮措施,其一次侧导线应采用橡皮护套电缆线,不得使用塑料线,二次侧导线不得破皮裸露。

12.3.10、施工现场所用配电箱必须符合部颁标准的规定,并由主管电器工程师审验,安全部监督检查合格方可使用。

12.3.11、配电系统在采用接地和接零保护方式的同时,必须设两级漏电保护装置,实行分级保护,形成完整的保护系统。漏电保护装置的选择应符合规定。

12.3.12、施工现场临时用电系统的配电箱必须设置围栏,并配以明显的安全警示标志。

12.3.13、严禁雷电交加、大雨时不得触摸电线或接地装置,以防雷击伤

第13章 附图

项目部驻地临时用电平面布置图,(附图一); 项目部驻地临时用电系统图 ,(附图二): 施工现场临时用电平面布置图,(附图三); S1、S2施工现场临时用电系统图 ,(附图四、五):